A program manager overseeing multiple interrelated projects notices that small schedule delays in one project are causing ripple effects across the entire program. The current risk registers and project plans are maintained independently. What should be done to better handle these cross-project uncertainties?
Correct Answer: B. Conduct integrated risk management at the program level.
In complex environments with multiple interdependent projects, risks should be analyzed across projects, not in isolation. Program-level risk management identifies systemic and cascading risks, enabling proactive coordination and strategic decision-making across the portfolio.
Why the other choices are wrong: