Question

A project manager accepts a delivery at the project site but the items are of a poor quality. The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected.

What should the project manager do going forward?

 

Answers
  1. correct
Explanation

The correct answer is: Review the contract requirements and ask for the applicable evidence for quality assurance.

The project manager should first review the contract to understand the quality standards and requirements agreed upon with the vendor. By requesting applicable evidence for quality assurance, such as certifications or inspection reports, the project manager can ensure that future deliveries meet the necessary quality criteria. This proactive approach helps mitigate risks associated with poor-quality materials and establishes accountability with the vendor for upcoming deliveries.

 

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

GPHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered