A highly critical project is in jeopardy due to missing professional resources. What should the newly assigned project manager do first?
Correct Answer: B
When a critical project lacks necessary professional resources, the project manager should first try to locate qualified professionals within the organization.
This approach is usually faster and more cost-effective than hiring externally, as internal team members are often more familiar with the organization’s processes and project needs. By promptly addressing the resource gap with internal expertise, the project manager can help stabilize the project and keep it moving forward efficiently.