A customer discovered quality issues with the latest deliverables. However, the project team immediately resolved the issues.

Now that the project is back on track, what should the project manager do next?

Answers
  1. correct
Explanation

The correct answer is: D

The project manager should conduct a lessons learned session to analyze the quality issues that arose with the latest deliverables. This process allows the team to identify the root causes of the problems, discuss what went wrong, and document effective solutions. By capturing these insights, the project manager can implement preventive measures and improve processes, reducing the likelihood of similar quality issues in future project phases.

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

GPHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered