A healthcare technology project team creates a detailed plan - PMP Practice Questions

Question

A healthcare technology project team creates a detailed plan for the next sprint but leaves the final testing and deployment phases in a high-level form to be elaborated later. What type of planning approach is being used?

 

Answers
  1. correct
Explanation

Correct Answer: C. Rolling wave planning
Rolling wave planning involves progressive elaboration—planning work in detail as it approaches in time while keeping distant tasks at a higher level. Here, the team details the next sprint but postpones planning for later phases. This allows teams to remain flexible and adapt as more information becomes available closer to execution.

Why the other choices are wrong:

  • A. Predictive planning would require a full detailed plan from the beginning.
  • B. Just-in-time planning relates to scheduling tasks immediately before execution, not phased elaboration.
  • D. Bottom-up planning builds plans by aggregating detailed tasks, but it doesn't inherently involve phased or deferred detail.

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered