Your project is 25 complete when you discover that the budge - PMP Practice Questions

Question

Your project is 25% complete when you discover that the budget at completion (BAC) is no longer viable. You try to come up with a forecasted estimate at completion (EAC).

What index can you use to look at the calculated projection of cost performance that must be achieved on the remaining work?

Answers
  1. correct
Explanation

The correct answer is: B. To-Complete Performance Index (TCPI).

The To-Complete Performance Index (TCPI) is used to determine the cost performance that must be achieved on the remaining work in order to meet a specified management goal, such as the Estimate at Completion (EAC). When the budget at completion is no longer viable, TCPI helps project managers assess the efficiency required for the remaining tasks to bring the project in line with the revised forecast. It essentially shows the level of cost performance needed to complete the project within the updated budget.

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered