You are explaining resource leveling to one of your team members. You can tell any of the following statements about resource leveling, EXCEPT?

Answers
  1. correct
Explanation

The correct answer is D

The statement that is not true about resource leveling is "Resource leveling is applied to a schedule before it has been analyzed by the critical path method." 

Resource leveling  occurs after the critical path method (CPM) has been applied, as CPM identifies the longest sequence of dependent tasks and helps determine the minimum project duration.

Effective resource allocation relies on understanding the critical path, making it essential to analyze it before applying resource leveling.

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

GPHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered