Question

This graph describes the current performance of a project in relation to cost and schedule. What should the project manager do to bring the project back on track?

Answers
  1. correct
Explanation

The Correct Answer is A

If the graph shows that the schedule indicators ("S") are below 1 (indicating the project is behind schedule) and the cost indicators ("C") are around or above 1 (indicating the project is under budget), then the project manager should focus on reviewing the project schedule to identify delays and bring the project back on track. Focusing on the schedule rather than cost is appropriate here since the project appears to be financially on track but lagging in timeline

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

GPHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered