This graph describes the current performance of a project in relation to cost and schedule. What should the project manager do to bring the project back on track?
The Correct Answer is A
If the graph shows that the schedule indicators ("S") are below 1 (indicating the project is behind schedule) and the cost indicators ("C") are around or above 1 (indicating the project is under budget), then the project manager should focus on reviewing the project schedule to identify delays and bring the project back on track. Focusing on the schedule rather than cost is appropriate here since the project appears to be financially on track but lagging in timeline