The project sponsor recently requested that a vendor begins - PMP Practice Questions

Question

The project sponsor recently requested that a vendor begins working toward adopting a hybrid approach. In response, the vendor hired a project manager experienced in agile for the project. What does that project manager need to do to make the team work in a collaborative way?

Answers
  1. correct
Explanation

The Correct Answer is: B

To enable a smooth transition to a hybrid approach, the project manager should first assess the team's readiness and identify any training gaps. Moving to a hybrid model often requires team members to be familiar with both traditional and agile methodologies. By identifying these gaps, the project manager can ensure that team members have the necessary skills and understanding to work collaboratively and effectively in the new approach. Addressing training needs upfront is key to fostering a cohesive team environment and ensuring alignment with the project’s hybrid methodology.

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered