The project sponsor gives you a project charter and asks you - PMP Practice Questions

Question

The project sponsor gives you a project charter and asks you to start working on the project immediately and to provide him with a schedule. What should you do first?

Answers
  1. correct
Explanation

The correct answer is A

After receiving the project charter, the first step should be to begin creating a project scope statement. This document outlines the project's objectives, deliverables, and boundaries, providing a solid foundation for all subsequent planning activities.

Establishing a clear scope ensures alignment with stakeholder expectations and helps prevent scope creep. Once the scope is defined, you can effectively create an activity list and estimate the necessary activities to complete the project successfully.

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered