The project sponsor gives you a project charter and asks you to start working on the project immediately and to provide him with a schedule. What should you do first?
The correct answer is A
After receiving the project charter, the first step should be to begin creating a project scope statement. This document outlines the project's objectives, deliverables, and boundaries, providing a solid foundation for all subsequent planning activities.
Establishing a clear scope ensures alignment with stakeholder expectations and helps prevent scope creep. Once the scope is defined, you can effectively create an activity list and estimate the necessary activities to complete the project successfully.