Question

The project optimistic estimate is 10 weeks and the pessimistic estimate is 40 weeks. What is the standard deviation of the estimate?

Answers
  1. correct
Explanation

The correct answer is B.

To calculate the standard deviation using the three-point estimate method, we can use the following formula:

Standard Deviation(σ)=P−O6Standard Deviation(σ)=6P−O​

Where:

  • OO = Optimistic estimate (10 weeks)
  • PP = Pessimistic estimate (40 weeks)

First, calculate the difference between the pessimistic and optimistic estimates:

P−O=40−10=30 weeksP−O=40−10=30 weeks

Now, substitute this value into the standard deviation formula:

σ=306=5 weeksσ=630​=5 weeks

Thus, the standard deviation of the estimate is b. 5 weeks.

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

PMP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

GPHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered