The project optimistic estimate is 10 weeks and the pessimistic estimate is 40 weeks. What is the standard deviation of the estimate?
The correct answer is B.
To calculate the standard deviation using the three-point estimate method, we can use the following formula:
Standard Deviation(σ)=P−O6Standard Deviation(σ)=6P−O
Where:
First, calculate the difference between the pessimistic and optimistic estimates:
P−O=40−10=30 weeksP−O=40−10=30 weeks
Now, substitute this value into the standard deviation formula:
σ=306=5 weeksσ=630=5 weeks
Thus, the standard deviation of the estimate is b. 5 weeks.