In a marine construction project, the project manager is informed by the marine authority that the work permit will not be issued until certain environmental reinforcement work has been completed. After reviewing the project management plan,the reinforcement work is not included in the project scope.
What should the project manager do?
The correct answer is A
The correct action for the project manager to take is to Start the organization's change control process via a change request.
Since the environmental reinforcement work required by the marine authority is not included in the original project scope, initiating a change request is the appropriate step. This formal process allows the project manager to document the need for additional work, assess its impact on the project’s timeline, budget, and resources, and seek approval from relevant stakeholders.
Starting the change control process ensures that all necessary adjustments are made systematically and that any implications of adding this work are considered. This approach maintains project integrity and compliance with organizational protocols while addressing regulatory requirements imposed by the marine authority.
No Payment Cards Needed
Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.
You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams