During the review of a projects list of deliverables one of - PMP Practice Questions

Question

During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?

Answers
  1. correct
Explanation

The Correct Answer is D

Reviewing the requirements traceability matrix is the best approach in this situation because it allows the project manager to systematically verify whether the requirement in question is indeed missing or if it has been addressed through other deliverables. The traceability matrix maps requirements to specific project deliverables, providing a comprehensive view of how each requirement is being met.

By going through this matrix with the concerned stakeholder, the project manager can identify any gaps or misalignments, and then work to resolve the issue. Reviewing the traceability matrix collaboratively with the stakeholder ensures transparency, aligns understanding, and provides a structured path to addressing the stakeholder's specific concern.

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered