During the first project meeting with a new project manager, a stakeholder complains about not receiving periodic reports. What should the project manager do first?
Correct Answer: A
The project manager's first step should be to meet with the stakeholder to understand their expectations regarding periodic reports. By doing so, the project manager can clarify the specific type of information the stakeholder needs, the desired frequency of updates, and any preferred formats. This personalized approach ensures that the stakeholder’s needs are accurately understood and addressed. Once these expectations are clear, the project manager can update the stakeholder engagement plan to ensure ongoing, consistent communication that aligns with the stakeholder's requirements, helping to build trust and prevent future communication issues.
No Payment Cards Needed
Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.
You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams