During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays. On which area should the project manager focus?
The Correct Answer is: C
When conflicts among stakeholders lead to approval delays, it suggests that some stakeholders may feel their perspectives or concerns are not adequately addressed. By revisiting the stakeholder engagement plan, the project manager can identify any overlooked or insufficiently engaged stakeholders and adjust the plan to improve communication and alignment. Focusing on effective stakeholder engagement can help resolve conflicts, foster collaboration, and reduce delays in approvals, ultimately helping to keep the project on track. This approach addresses the root cause of the delays, rather than just the symptoms.
No Payment Cards Needed
Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.
You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams