During project initiation meetings, the project manager of a 9-month project states that a specific task would be out of schedule. At the project kick-off meeting, a key project stakeholder strongly objects, stating that this task is the key value of the project and should be completed on time.

What should the project manager do to reduce the chances of having a strong rejection from stakeholders during the project initiation stage?

Answers
  1. correct
Explanation

The correct answer is: A

Schedule meetings with key stakeholders in advance to gather feedback on the project scope.

To reduce the chances of strong rejection from stakeholders during the project initiation stage, the project manager should proactively schedule meetings with key stakeholders to gather their feedback on the project scope. This collaborative approach allows stakeholders to voice their concerns and expectations early on, fostering buy-in and alignment. By involving them in discussions, the project manager can address potential objections before they escalate, leading to smoother project initiation.

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered