At the end of a meeting a functional manager takes the proje - PMP Practice Questions

Question

At the end of a meeting, a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project. What should the project manager do in this situation?

 

Answers
  1. correct
Explanation

The correct answer is: Advise the functional manager and the project team member to review the resource management plan.

In this situation, the project manager should direct both the functional manager and the team member to review the resource management plan, as it outlines roles, responsibilities, and expectations for each team member. This approach ensures that the team member gains clarity about their specific contributions to the project. It also fosters communication between the project manager and functional manager, promoting a collaborative environment for resolving role-related concerns.

 

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered