As a project manager you are reviewing a report of the actua - PMP Practice Questions

Question

As a project manager you are reviewing a report of the actual cost of the completed work packages. You realize that a few work packages are completed with an actual cost which is substantially lower than their budgeted cost.

You will immediately do all of the following actions except?

Answers
  1. correct
Explanation

The correct answer is 1. Try to find ways to increase the actual costs.

As a project manager, it is not advisable to find ways to increase actual costs when work packages are completed under budget. Instead, your focus should be on ensuring that the proper resources were used, the scope was fully delivered, and the quality of work was not compromised. If all requirements have been met within the reduced cost, this could simply reflect increased efficiency. Increasing costs for the sake of aligning with the budgeted amount would be counterproductive and unethical.

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered