An agile project has a documented list of requirements prior - PMP Practice Questions

Question

An agile project has a documented list of requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult to know what to work on next as so many items are listed as high priority.

What should the project manager recommend?

Answers
  1. correct
Explanation

The correct answer is: B

Ensure the product owner determines the priority based on a product roadmap, release plan, and iteration plan.

In Agile projects, the Product Owner is responsible for defining and prioritizing the product backlog. They do this by taking into account the product roadmap, release plan, and iteration plan to ensure that the highest-value features are delivered first. This approach helps align the team’s work with the overall business goals and customer needs, removing ambiguity in prioritization.

 

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered