All the following happen in the initiating process with the - PMP Practice Questions

Question

All the following happen in the Initiating process with the exception of:

Answers
  1. correct
Explanation

The correct answer is a. 

In the Initiating process group, activities such as determining stakeholders, identifying processes and standards, and creating the project charter are all essential tasks. However, choosing the project team typically occurs during the Planning process group, where the project manager assesses resource needs and selects team members based on the skills required for the project. Thus, choosing the project team does not happen in the Initiating process.

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered