Question

After a project status meeting, the project manager realizes that the project is under budget, quality checks are positive, and the schedule variance is negative. How should the project manager qualify the project status?

 

Answers
  1. correct
Explanation

Despite being under budget and having positive quality checks, the negative schedule variance indicates that the project is not progressing as planned within the established timeline. This status suggests that the project is experiencing delays, which could impact future deliverables and overall project success. By recognizing the project is behind schedule, the project manager can focus on identifying the root causes of the delays, implementing corrective actions, and communicating effectively with stakeholders to realign expectations and ensure that the project gets back on track.

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

GPHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered