A technical subject matter expert sme identifies an occurren - PMP Practice Questions

Question

A technical subject matter expert (SME) identifies an occurrence that should be captured in the project's lessons learned. The SME asks the project manager to write, document, and include it in the lessons learned register.

What should the project manager do?

Answers
  1. correct
Explanation

The correct answer is B

The project manager should ask the SME to document and capture the occurrence. Since the SME has direct knowledge and expertise about the situation, they are best positioned to accurately record the details and implications. While the project manager oversees the lessons learned, it is more efficient for the SME to provide first-hand documentation.

This ensures accuracy and completeness in the lessons learned, which can be reviewed and formalized later by the project manager. Waiting until project closure could result in lost details, and assigning it to another team member might lead to miscommunication or incomplete information.

 

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered