A team is currently working on a mobile app solution during - PMP Prep

Question

A team is currently working on a mobile app solution. During sprint execution, one of the developers requires clarification about the acceptance criteria for a particular task. What should the project manager do to obtain the information required by the developer?

 

Answers
  1. correct
Explanation

Correct Answer: B

In an agile project, the product owner is responsible for defining and clarifying acceptance criteria for tasks, as they represent the customer’s voice and have in-depth knowledge of the requirements. By working with the product owner, the project manager ensures that the developer receives accurate information aligned with the product vision and priorities. This approach also keeps communication channels clear and prevents unnecessary delays by directly involving the role best suited for clarifying requirements within the agile framework.

 

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

GPHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered