A project manager uses a laissezfaire leadership style with - PMP Practice Questions

Question

A project manager uses a laissez-faire leadership style with a newly hired project team. The project manager quickly notices that team members are underperforming, the schedule is delayed, and the project is overbudget.

What should the project manager have done at the start of the project?

 

Answers
  1. correct
Explanation

The correct answer is: Adapted a direct management style according to the project team's needs.

At the start of the project, the project manager should have adopted a direct management style tailored to the team's specific needs. This approach would involve setting clear expectations, providing guidance, and closely monitoring progress, especially for a newly hired team that may require more direction. By actively engaging with the team, the project manager could have addressed performance issues early, ensuring that the project remained on schedule and within budget.

 

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered