A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late, digress into solutioning, or skip the meetings altogether.
How should the project manager improve this situation with the project team?
The Correct Answer is C: Engage the project team in implementing and improving key aspects of the standup meetings.
This approach fosters ownership and accountability among team members, encouraging them to contribute to the effectiveness of the standup meetings. By involving the team in discussions about the purpose, structure, and rules of the meetings, the project manager can help them understand their value and relevance.
This collaborative effort can lead to improvements in attendance, punctuality, and focus during the meetings, ultimately enhancing team dynamics and project progress. Engaging the team in this way also helps build a culture of continuous improvement, which is essential in a hybrid approach
No Payment Cards Needed
Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.
You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams