A project manager is assigned to a regulatory project for their country. The deadline for delivering results in compliance with the new laws is very tight, and the project team members have not yet been assigned. One of the project manager's peers informs the project manager that a project with the same scope for a different country was completed 1 year ago. What should the project manager do first?
Correct Answer: B.
In this situation, the project manager should first review organizational process assets (OPAs), which may include documentation, lessons learned, and estimates from the similar project completed the previous year. By leveraging analogous estimating, the project manager can develop an initial project timeline and resource estimate based on the historical data from the past project with a similar scope. This approach allows for a faster estimation process, which is crucial given the tight deadline, and provides insights that can guide planning and resource allocation decisions effectively.
No Payment Cards Needed
Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.
You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams