A project manager decided to use a highly adaptive approach - PMP Practice Questions

Question

A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.

What should the project manager do next?

Answers
  1. correct
Explanation

The correct answer is: B

The project manager should explain the higher-level objectives to be assigned to the team. In an adaptive project management approach, it is crucial to establish a clear understanding of the overall project goals and objectives. By sharing this information with the team, the project manager ensures that everyone is aligned and working towards the same purpose.

This alignment helps the team make informed decisions during the iterative process and fosters a sense of ownership and commitment. Additionally, understanding the higher-level objectives allows the team to adapt their plans and strategies more effectively as the project progresses, ensuring that the final outcome meets the desired goals.

 

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered