Question

A project just kicked off and management's expectation is to ensure that the deliverable of the first iteration helps the marketing team present the product prototype to potential customers. What should the project manager do?

 

Answers
  1. correct
Explanation

Correct Answer: C

To meet management's expectation of presenting a product prototype to potential customers in the first iteration, the project manager should identify the minimum functionality required for the product. This approach aligns with creating a minimum viable product (MVP) that includes essential features to showcase the product concept and value to stakeholders, including potential customers. By focusing on the minimum functionality, the team can prioritize development efforts on critical aspects, ensuring a timely and effective delivery that meets the immediate needs of the marketing team without overextending resources on non-essential features at this stage.

 

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered