A construction company is executing a building contract that - PMP Practice Questions

Question

A construction company is executing a building contract that includes firm milestones for replacing certain components of the building. During execution, the client complains that the new components do not meet the requirements.

What should the project manager have done to prevent this from happening?

 

Answers
  1. correct
Explanation

The correct answer is: Defined acceptance criteria in a quality checklist agreed upon before starting the build phase.

To prevent the issue of components not meeting requirements, the project manager should have established clear acceptance criteria through a quality checklist prior to the build phase. This ensures that both the construction team and the client have a mutual understanding of the expectations and standards for the components. By having agreed-upon criteria, it becomes easier to verify compliance during execution, reducing the likelihood of disputes and ensuring client satisfaction.

 

No Payment Cards Needed

Related Courses

Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.

a prepsaret exam featured image
Career Prep

SHRM-SCP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SHRM-CP Test Prep

Start Course Prep
a prepsaret exam featured image
Career Prep

SPHR Practice Test

Start Course Prep
a prepsaret exam featured image
Career Prep

PHR Practice Test

Start Course Prep

Easy way to pass your test within a week with prepsaret

You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams

View Courses Offered