A company is starting a critical project with a strict deadline. During the first planning meeting, the team realizes that the list of requirements has too many items to allow on-time delivery.
What should the project manager do first?
The correct answer is A
The project manager should ask the team to propose a minimum viable product (MVP) to meet the date. This approach ensures that the most critical features or requirements are delivered within the strict deadline, while less essential items can be deferred to future iterations.
Focusing on an MVP enables the project to stay on track, delivering value to the customer without overwhelming the team. Simply increasing the team's capacity or suggesting backlog reduction may not be feasible or desirable without first understanding what is absolutely necessary to meet the project's goals. The MVP approach balances time, scope, and quality effectively.
No Payment Cards Needed
Discover a range of courses designed to provide you with the knowledge and skills needed to excel in your chosen field.
You don’t need one month to study and pass your test.
With Prepsaret, it takes you a few days to grasp all the concepts needed to pass your exams